The problem
Under the slabs there was almost no MOT Type 1 (the crushed stone base a patio sits on): 20mm at most, and some you could wipe away with your hand. Parts sat on bare mud, with no membrane.
How we solved it
We lifted the sinking slabs and dug out what was under them. Then we laid a membrane (a sheet that stops the base mixing into the soil) and a proper, compacted MOT Type 1 sub-base, and relaid the slabs with fresh pointing.